Thursday, February 27, 2020

Edge Metal and Cap Sheet installed! Roof Complete

Today the students and I installed the drip edge metal and 2nd ply (final) roofing! For the edge metal we placed a second 9"strip of Flintflash and set the edge metal in a bonding agent and primed the edge metal. We nailed the edge metal at a min. of 6"OC.  We then laid the second and final cap sheet on the roof. On the cap sheet we nailed 16" OC at the 3 inch edge strip. We made one penetration for a 1 1/2 inch VTR. We placed the vent cap on top of the exist midply, placed bead of caulk and nailed it down with roofing nails. We then laid another 9" step of midply before placing cap sheet over it. We then beaded around the edge of the cap sheet and metal.