The week may be broken up into outside work/ inside work depending on rain.
Tiny Home: inside Work
Update Blog pages.
Design considerations:
KITCHEN
What goes into the kitchen - sink, stovetop, oven, vent, refrigerator, toaster, microwave, countertop, outlets, lights, light switches, fixtures, cabinets,
BATHROOM
What goes into the bathroom - sink, toilet, shower, outlets, lights, light switch. shower door, storage, countertop, vent, fixtures, cabinets
LOFT
Where does light, light switches, electrical outlets, cabinets, ladder, vent, bed, clothing storage
LIVING SPACE
outlets, lights, light switches, sofa, storage, TV, computer space, desk, clothing storage,
FRONT DOOR
Type of door, lights, switches,
RAIN - We had rain on Wednesday, Dec 4 and Friday, Dec 6. We had to tarp the tiny home Tuesday, and again Friday.
Tiny Home: Outside Work
This week the goal is to complete the roof rafter installation and tie up any loose corners, such as having the correct number of nails supporting the loft and placement of some horizontal 2 x 4 at joints of plywood etc.
We also need to complete the double top plate of the upper wall.
Frame in for a window on the loft.
No comments:
Post a Comment